Pre-Feasibility Study of Photovoltaic Plants (PV) 10 MW, Fier Municipality

Client: Non-Public
Partners: N/A
Construction Cost: Not Public
Contract Period: 06/2018 – 07/2018
The photovoltaic (PV) plant with the maximum installed power of 10MW, is planned to be built in Fier Municipality. From the preliminary assessment and analysis of the solar radiation and other necessary data it has resulted that the average electricity produced by the plant is 15’947’773 kWh or 15’947.8 MWh. The study is based on solar radiation data and computer modeling that is performed using data.
The main services provided within this Project were as those below:
• General Arrangement of Power Plant
• Single Line Diagram
• Connection to Grid
• Analysis & Evaluation of Solar Radiation
• Evaluation of Average Annual Energy
• Cost Estimation
• Environmental and Social Impact Assessment