Study and Design the Engineering Measurement in the Road Rubik Rreshen-Gjegjan

Client: General Roads Directorate of Albania
Partners: N/A
Construction Cost: 2.8 Million USD
Contract Period: 10/2007-12/2008
Project consists in detailed design for reinstating of 14 spots that have incurred structural failure in the national road axis Rubik RreshenGjegjan. Mainly the spots had slope stability problems, while one spot had structural failure of a bridge and one spot was to protect the road slope from Fani river for about 400m. The assignment was to determine the real causes of the failures, to evaluate the existing structures and foundations and design the reinforcement measures.