Bankable Feasibility Study of a River Cascade 25MW, Albania

Client: Not Public
Construction Cost: 22,000,000 EUR
Contract Period: 05/2015-07/2015
Project consists in feasibility study of the Hydropower Plant of a River Cascade located in north of Albania with installed power of 25 MW and annual estimated energy production of 80 GWh. The components handled technically by ICE are: overflow weir, lateral water intake, settling basin, 1 km open channel, 4 km GRP derivation penstocks 1500-2000 mm, 8 km free flow tunnel, 1 km of pressure tunel, forebay, powerhouse, tailrace, substation, and temporary works such as access roads and site camp.