Bankable Feasibility Study of HPP 4, Albania

Client: Not Public
Partners: N/A
Construction Cost: 1,700,000 USD
Contract Period: 02/2013-03/2014
Project consists in feasibility study of the Hydropower Plant located in Elbasan, with installed power of 800 kW and annual estimated energy production of 5.4 million kWh. The components handled technically by ICE are: hydrological study, overflow weir, drop water intake, settling basin, forebay, penstock 3000m long with 500mm dia, powerhouse, tailrace, substation, and temporary works such as access roads and site camp. Detailed design services will be provided under another assignment.